Fertiliser Bulk Storage Facility
Client
Qube Ports and Bulk
Build Time
14 weeks
Location
Rockingham
Contract Type
Design and Construct
Value
$4M
QDC Designed and Constructed a new 5,000m² bulk storage facility to retain fertiliser materials. We were engaged by the client to redesign a non-viable project and deliver a cost-effective solution.
At the highest point, the building is 15m to ensure that fully laden semi-trailers could end tip into the facility. QDC were given a tight deadline as deliveries to the facility were ordered before the project commenced, and construction was successfully completed in 14 weeks.